Mark Twain Transmission Line Meetings

Each month the Adair County Commissioners meet with Mark Twain Transmission Project Representatives to receive landowner real estate updates and construction progress regarding the Mark Twain Transmission Line. 

This month the Adair County Commissioners met with members of the of the Mark Twain Transmission Project Team on Monday June 11, 2018.   

The construction of the Mark Twain Transmission Project, in Adair County, began in May 2018.  The construction process includes the Zachary Substation ground-breaking, the creation of access points along the transmission rights of way, and the installation of foundations on specific parcels.

Land agents continue to work with landowners on the easement acquisition process and right of entry permission for the necessary survey work.

In preparation for the construction process, Mark Twain will be notifying landowners on active construction line segments but construction will not begin on any parcel without a signed easement agreement.

Additionally, property owners with signed easements will be contacted in person, phone or in writing at least 24 hours prior to the beginning of construction on their property.

Mark Twain and the Commissioners are appreciative of the landowners and communities’ cooperation during these important milestones of the Mark Twain Transmission Project.